KARIBU JILORE PROJECT
The great news is that Karibu Onlus Kenya has been recognized as a charitable organization and entered into the official register of associations in Kenya; it is therefore authorized to operate freely in the country, in compliance with local laws. This means that our project in Jilore can now begin; it will follow the same model as the Chakama project, although the people involved will be different. Essentially, new micro-projects will be added, along with a new approach to managing funds and overseeing the execution of all project-related work.
So, officially, KARIBU ONLUS ITALIA will continue to collect funds to be transferred to KARIBU ONLUS KENYA at the appropriate time to make all necessary payments.
Chakama has taught us a lot, so we will not repeat the same mistakes born, then, from pure enthusiasm and the frenetic urgency to do, do and do, which sometimes led us to make mistakes along the way.
Our relationship with the Jilore community will be different: more collaborative, more hands-on, even more proactive, and certainly more responsible.
As always, only time will tell about this new adventure.
THE PROJECT
PP1/PP2
We began last year by building the first classroom, and today we are ready to complete the project in time for the start of the school year in January 2027.
WELL
This will be a cornerstone of the entire projet, serving as a vital resource to connect all the facilities we plan to build. It will be made available to the entire community free of charge.
Work on the well will begin concurrently with the construction of the PP2 classroom.
AGRICULTURE AND FARM
This is a brand-new feature of the project.
We will have 3 acres at our disposal, dedicated to fruit and vegetable cultivation, animal husbandry, and the creation of a fish pond for raising tilapia.
This area is expected to become self-sustaining by the end of 2027, allowing future investments to be directed toward other public-benefit micro-projects.
WORK TIMING AND COSTS
2027
WELL
-
January 7, 2027: First down payment for the initial materials needed to build the well. €1,000
-
January 22, 2027: Second down payment to continue construction of the well. €450
-
February 6, 2027: Final payment for the well construction work. €245.
-
TOTAL: €1,760
PP2
-
January 7, 2027: First down payment for the construction of the second kindergarten classroom, including restrooms. €2,500
-
January 22, 2027: Second advance payment of €2,000
-
February 6, 2027: Final balance of €1,500
-
TOTAL: €6,000
-
-
Hexagonal tables and chairs
-
TOTAL €1900